Yes, if the deck surface is more than 600 mm (2 ft) above the ground. Here are the City of Kingston's actual rules, what the drawings need to show, and the three inspections, plus a 20-second checker.

The 600 mm rule

The City of Kingston requires a building permit for any deck whose walking surface is more than 600 millimetres above grade. Decks at or below 600 mm don't need a permit, but they still have to comply with the City's Deck Bylaw for setbacks from property lines. That's the whole test: measure from the ground to the top of the decking at the highest point.

Pergolas and roofs over a deck, and sheds or accessory buildings over 10 m², need their own permits regardless of height.

What a Kingston deck permit application includes

  • Application through the City's DASH online portal, with the Schedule 1 Designer Information form
  • A scaled site plan showing the house, the deck and all setbacks
  • Construction drawings: footings, posts, beams, joists, decking, stairs (rise and run), handrail and guard details
  • A locates form confirming underground utilities have been marked
  • The permit fee, set by the City's building fee schedule

We prepare and submit the whole package as part of the job. You sign; we handle the rest.

Do I need a deck permit in Kingston?

Based on the City of Kingston deck rules. Two questions.

How high will the deck surface be above the ground?
Will it attach to the house?

Result

Answer two questions

We check the rules for your address at the site visit, and we prepare the drawings and application when a permit is needed.

Kingston deck code requirements at a glance

City of Kingston deck requirements (confirm current fees with Building Services)
ItemKingston requirement
Permit thresholdDeck surface more than 600 mm above grade
FootingsSono tube minimum 230 mm diameter, 1.2 m below finished grade, 150 mm above grade
Guard height900 mm where the deck is under 1.8 m above grade; 1,100 mm when over 1.8 m
Guard openingsNo opening that passes a 100 mm sphere
InspectionsExcavation (post holes, before concrete), framing (before decking and guards), final
BookingEach inspection booked 24 hours ahead
Accessory structuresOver 10 m² needs a separate permit

Source: City of Kingston, Deck construction permits and the deck permit guide. The Ontario Building Code is published by the Province of Ontario.

Outside Kingston?

Loyalist Township (Amherstview, Odessa, Bath), Greater Napanee, South Frontenac and Prince Edward County each issue their own building permits. The Ontario Building Code sets the structure; the local bylaw sets the setbacks. We check your municipality's rules at the site visit. See our service area for who we deal with where.

Once you know whether you need a permit, the next question is price. Our deck cost guide covers it, and the deck builders page shows what we build.

FREE, WRITTEN, NO PRESSURE

Get a deck estimate, permit included

Send a few details and we'll call to book a site visit. Photos help, and you can send them once we reply. If you used a tool on this page, your answers come through with the form.

Phone: 343-459-7466
Hours: Mon to Fri, 8 am to 5 pm
Office: 945 Princess Street, Kingston, ON K7L 3N6

We reply within one business day. Prefer to talk? Call 343-459-7466.

Deck permit questions

How high can a deck be without a permit in Kingston?

Up to 600 mm (about 2 feet) from the ground to the deck surface. Above that, the City of Kingston requires a building permit. Other municipalities in our area use similar thresholds, but check yours.

How much does a deck permit cost in Kingston?

The fee comes from the City's building permit fee schedule and depends on the deck's size. We bill it at cost on your estimate. Expect a few hundred dollars for a typical residential deck; we confirm the current figure when we apply.

What drawings do I need for a deck permit?

A scaled site plan showing the deck's location and setbacks, plus construction drawings: footing size and depth, post and beam sizes, joist size and spacing, decking, stair rise and run, and guard details. We prepare all of it.

How many inspections does a deck need?

Three in Kingston: post holes before concrete, framing before the deck boards and guards go on, and a final inspection. Each is booked 24 hours ahead. We schedule and attend them.

What happens if I build a deck without a permit?

Building without a required permit is an offence under the Ontario Building Code Act. The City can order the deck removed or opened up for inspection, and unpermitted work can surface when you sell. It's not worth it.

Does a freestanding deck need a permit?

If it's more than 600 mm above grade, yes, attached or not. Freestanding decks under that height usually don't, though setbacks still apply.